We've detected that you're using an ad content blocking browser plug-in or feature. Ads provide a critical source of revenue to the continued operation of Silicon Investor.  We ask that you disable ad blocking while on Silicon Investor in the best interests of our community.  If you are not using an ad blocker but are still receiving this message, make sure your browser's tracking protection is set to the 'standard' level.
Strategies & Market Trends : Countries

 Public ReplyPrvt ReplyMark as Last ReadFilePrevious 10Next 10PreviousNext  
From: Sam Citron3/20/2009 1:58:16 PM
   of 264
 
Kuwait Cancels Refinery Contracts [WSJ]
By MIKE BARRIS and OLIVER KLAUS

Kuwait National Petroleum Co. has canceled more than $10 billion in contracts for a refinery project, including $2.1 billion in remaining value to Fluor Corp., amid the slump in fuel prices and the project's burgeoning cost.

Share of Fluor, which reported the cancellation of its contract Friday, fell 3.6% to $37.42 in premarket trading as the move will cut the company's backlog as of Dec. 31 by some 6%.

Four South Korean companies earlier said the state-run Kuwaiti oil firm canceled $8.36 billion in refinery orders awarded them in May.

The $15 billion refinery project appeared in limbo earlier this week days after it was reported that Kuwait's former prime minister had ordered its cancellation in a further sign that political chaos in the state was taking its toll. Both the project's sponsor, KNPC, and the international contractors building the refinery said earlier this week they were unaware the project had been scrapped.

Kuwait's ruler dissolved Parliament Wednesday and called for fresh elections, a move that could end weeks of a political deadlock that has stalled an economic bailout program for the Gulf nation's banks.


The project came under increased scrutiny last year after opposition members of Parliament alleged that KNPC's contract awards didn't comply with the tender procedures set out by Kuwait's Central Tenders Committee, which handles all public sector contracts. The project was subsequently referred to the State Audit Bureau, the country's accounting watchdog.

The project's scrapping comes three months after Kuwait's Parliament forced state-owned Petrochemical Industries Co. to pull out of a planned $18 billion joint-venture deal with U.S. chemicals giant Dow Chemical Co.

Fluor had approximately 300 employees performing engineering work on the al-Zour project. The refinery was to have been Kuwait's fourth, handling 615,000 barrels a day of crude, with the intent of producing low-sulfur fuel oil for the country's power plants from 2012.
Report TOU ViolationShare This Post